Thursday, September 17, 2009

Permit Approvals, as in Many!

A big day at the house. We had the city inspector by and got multipile items approved and signed off:

Electrical Rough-in - Had to add one plug but otherwise no problems

Gas Piping - Straight forward/done

In Floor Heating - All the second floor tubing, piping and thermostats approved

Framing - All the framing for the house approved


This sets us up to do the insulation and drywall next. Everything is moving along nicely :-)


Plus the siding continues. We are actually 100% done with the garage/west side and the front of the garage now.